Construction Cost Escalation in 2026: What’s Driving the Increase?

  • Oct 12, 2026

Construction Cost Escalation Expected to Accelerate in Second Half of 2026

Non-residential construction costs are expected to rise more quickly in the second half of 2026 than in the first half, driven by industry, economic, and political factors.

These findings are part of The Beck Group’s 2026 Construction Cost Report, Edition 2. The report examines the market forces influencing construction costs and provides updated cost data across the firm’s markets and building types.

Beck’s 2026 construction cost escalation projections range between 4.1% and 4.6%. Nationally, the mid-range rose from 4.25% to 4.35% because energy prices are expected to affect costs. Historically, annual cost escalation has typically been just under 4%.

Construction Cost Escalation in 2026: What’s Driving the Increase?

 

Construction input costs this year notably include higher prices for key building materials, mainly aluminum, steel, and copper products, largely because of tariffs and robust data-center growth.

Beck’s latest forecast assumes the following:

  • No future energy shocks
  • No substantial changes to certain materials
  • Continued labor constraints
  • Tighter U.S. monetary policy
  • No major near-term policy surprises
  • No major shocks to construction wages

Data Centers Powering Activity, Energy Markets Impacting Costs

A proliferation of data center buildouts across the country remains one of the brightest spots in the industry sectors, driven by torrid demand for AI and cloud computing.

Data-center building activity is strongest in the Sunbelt region, with Texas ranked as the nation’s second-highest location for data-center growth.

The data center boom is attracting skilled workers, primarily electricians and HVAC technicians, who are given higher wages and other incentives. While this activity is supporting construction backlogs, it is also further constraining the availability of skilled labor in other sectors.

Growing resistance to data center projects may put a dent in escalation. More state and local governments have banned data center facilities or imposed moratoriums, which could weaken demand for materials used in these projects.

Volatile energy markets remain a wild card for material costs. For example, this spring, the U.S.-Iranian conflict triggered a sharp rise in energy prices, pushing some material costs higher. Energy prices have since moved in a seesaw pattern amid sporadic Persian Gulf hostilities.

Improved Project Demand Seen

Despite headwinds, the industry has seen broad-based demand across sectors including healthcare, higher education, museums and other cultural facilities, hotels, faith-based facilities, and premium office buildings.

At the same time, older and underutilized office towers are increasingly being converted for residential or multi-use purposes. Adaptive-reuse projects have grown in popularity due to high office vacancies, housing shortages, and government funding for conversions that positively utilize existing building stock.

Inflation, Geopolitical Tensions Could Impede Growth

The industry still faces lingering inflationary pressures. Elevated, somewhat volatile inflation rates have dampened hopes for near-term interest rate cuts by the Federal Reserve. As a result, some owners and developers are experiencing difficulties financing projects because borrowing costs remain high, while others are pursuing projects despite the interest-rate environment.

Continued or escalating turmoil in the Middle East and other geopolitical conflicts could boost inflation and disrupt supply chains, potentially undercutting industry growth.

Backlogs Healthy, But Volatile

Construction backlogs continued to expand at a healthy pace in the first half of 2026, benefiting from infrastructure projects.

According to ABC, backlogs were at 8.0 percent in July, a notable decline from June. Contractors in the South, and large contractors, continue to have the longest backlog and the greatest stability through the July report, supported by digital and energy infrastructure projects.

Improved Architectural Billings Seen

Architectural firms expect to see gradual improvement in billings and signed design contracts in the coming months, barring major bearish events. Meanwhile, inquiries have strengthened since our last report, suggesting more owners are looking to resume paused projects or start new ones.

Larger firms, particularly those in the South, continue to show the greatest stability due to project diversification and an increasing number of large-scale projects. Smaller and less-diversified firms are most vulnerable to industry headwinds.